THE CONDO BOOK PROJECT

How Long Does AG Condo Plan Approval Take?

Updated · 4 min read

Short answer: The Attorney General has 30 days to answer each submission of a condo offering plan, but the median recent NYC plan took 215 days, about 7.1 months, from submission to acceptance (the average was 7.7 months), because plans usually go back and forth more than once. A quarter cleared in under 5.5 months, and a quarter took more than 8.9 months. These are the 100 most recent accepted plans with no amendments yet: 81 of them are in Brooklyn and 82 have ten or fewer homes, so they describe small Brooklyn plans best.

How the 30-Day Clock Works

The Martin Act gives the Attorney General 30 days to answer a condo offering plan: accept it for filing, or send a letter listing what's wrong (General Business Law § 352-e(2)). The 30 days run on each submission; the time between submissions, while the sponsor revises, isn't on the AG's clock. The figures cover the 100 most recent NYC condo plans that can be timed (no amendments yet), accepted since Jul 10, 2024: 81 in Brooklyn and 82 with ten or fewer homes. Each plan, with its dates, is on the approval times data page.

Until the plan is accepted for filing, the sponsor can't offer or sell units (§ 352-e(1)(a)). The AG's first answer is often a deficiency letter, a list of what must be fixed. The sponsor's lawyers revise the plan, often waiting on the architect's description of the building, a new budget or a tax program filing, and re-submit. Each re-submission gets its own review. So much of the wait is on the sponsor's (developer's) side, and a plan that answers the first letter completely can save time.

Acceptance isn't approval. The plan's cover has to say that filing "does not mean that the Department or any other government agency has approved" the offering (13 NYCRR 20.3(a)(7)). The AG reviews disclosure, not the building, the price or the sponsor. (What the plan contains.)

Time to Acceptance by Year

Year acceptedAverage timePlans
2026 (to date)7.6 months70
20258.9 months19
20246.1 months11

Samples per year are small, so read the figures as a guide rather than a trend.

What Makes an Offering Plan Slower

Average time from submission to acceptance
All plans7.7 months
New construction8.3 months
Rehabs and conversions6.7 months
Plans with ten or fewer units7.4 months

The 100 most recent NYC condo plans that can be timed, accepted since Jul 10, 2024.

Condo Book Researchcondobooknyc.com/research/condo-offering-plan-approval-time-nyc

The Plans That Don't Make the Average

The average only counts plans that were accepted. 608 NYC condo plans are listed as pending on the AG's record today, and 114 of them came in between 2015 and 2024, judging by the year in their plan ID. Those are years-long waits, or plans the sponsor stopped pursuing without withdrawing.

The AG rarely says no outright anymore. Its records show 86 NYC condo plans rejected from 2008 through 2016 and 3 since. A plan that can't get through now tends to sit pending or be withdrawn (52 since 2017).

What to Plan For

Look up any plan's dates by searching a building or sponsor, browse the newest NYC condo filings, or use the AG's database.

FAQ

How long does the NY Attorney General take to accept a condo offering plan?

Across the 100 most recent NYC plans that can be timed (mostly small Brooklyn plans), the median was 215 days, about 7.1 months, from submission to acceptance, and the average 234 days. A quarter took more than 8.9 months.

Doesn't the law give the AG 30 days?

Yes, for each submission. Within 30 days the AG must accept the plan or send a notice of deficiencies (GBL § 352-e(2)). Plans often get at least one deficiency letter, and each revised submission starts its own review.

Can a sponsor sell condo units before the plan is accepted?

No. The Martin Act bars offering or selling units until the plan is filed with the Attorney General.

Does new construction take longer than a rehab?

Among the most recent plans, new construction averaged 8.3 months against 6.7 months for rehabs and conversions.

Does "accepted for filing" mean the Attorney General approved the building?

No. The plan's cover must say the filing doesn't mean the Department of Law or any other agency approved the offering. The review is of the disclosure.

Why can only some plans be timed?

Once a plan is amended, the AG replaces the submission date on its record with the amendment's. So these figures count only plans with no amendments yet. They use the most recent plans, since old review times say little about today's, and leave out waits of two years or more as likely record errors.

Where do these figures come from?

From the NY Attorney General's offering plan records for the 100 most recent New York City condominium plans with residential units and no amendments, accepted since Jul 10, 2024, and the status of every NYC condo plan on the AG's record. Updated as of Nov 27, 2026.

Related: Choosing an Offering Plan Attorney: Who Will Push the AG for You? · What Is a No-Action Letter? How NYC Condos and Co-ops Skip the Offering Plan