Timeline
4 months from filing to approval3 days to certification · 4 months of public review
Application and environmental review3 days
- Application filedMar 28, 1980The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMar 31, 1980The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardJun 16, 1980 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJun 18, 1980 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJul 9, 1980 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedAug 21, 1980
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantOedOther Public Agency
Source: the NYC Department of City Planning's Zoning Application Portal, project P1980M0861, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.