15 Penn Plaza
09DCP019M: PROPOSES TO REDEVLOP THE CURRENT SITE OF THE HOTEL PENNSYLVA NIA WITH A NEW COMMERCIAL OFFICE BUILDING
- Outcome
- Approved
- Zoning map ULURP
- C100047ZMM
- Rezoned area
- 3.1 acres
- Law firm
- —
Timeline
1 year from filing to approval6 months to certification · 6 months of public review
Application and environmental review6 months
- Application filedAug 5, 2009The applicant files the land use application with the Department of City Planning.
- Environmental reviewOct 23, 2008 · through Feb 5, 2010An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewFeb 8, 2010 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardApr 19, 2010 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
- Borough presidentMay 19, 2010 · Conditional FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingMay 26, 2010 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJul 14, 2010 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilAug 26, 2010 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorAug 31, 2010 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedAug 31, 2010
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 09DCP019M · zoning map amendment C100047ZMM.
City Documents
Environmental review72 documents
- DEIS 00 Executive Summary
- DEIS 01 Project Description
- DEIS 02 Procedural and Analytical Framework
- DEIS 03 Land Use, Zoning, and Public Policy
- DEIS 04 Socioeconomic Conditions
- DEIS 06 Open Space
- DEIS 07 Shadows
- DEIS 08 Historic Resources
- DEIS 10 Neighborhood Character
- DEIS 11 Natural Resources
- DEIS 12 Hazardous Materials
- DEIS 14 Solid Waste and Sanitation Services
- DEIS 15 Energy
- DEIS 16 Traffic and Parking
- DEIS 18 Air Quality and Greenhouse Gas Emissions
- DEIS 20 Construction Impacts
- DEIS 22 Mitigation
- DEIS 24 Alternatives
- DEIS 26 Irreversible and Irretrievable Commitment of Resources
- DEIS Appendix A Zoning Text
- DEIS Appendix C Transportation Technical Memos and Analyses
- DEIS Appendix D Air Quality and Greenhouse Gas Emissions
- DEIS Appendix E Noise
- DEIS Cover Page and Table of Contents
- DEIS Notice of Completion Feb 5, 2010
- Draft Scope Of Work Dec 19, 2008
- EAS Dec 19, 2008
- FEIS 00 Executive Summary
- FEIS 01 Project Description
- FEIS 02 Procedural and Analytical Framework
- FEIS 03 Land Use, Zoning, and Public Policy
- FEIS 04 Socioeconomic Conditions
- FEIS 05 Community Facilities
- FEIS 06 Open Space
- FEIS 07 Shadows
- FEIS 08 Historic and Cultural Resources
- FEIS 09 Urban Design and Visual Resources
- FEIS 10 Neighborhood Character
- FEIS 11 Natural Resources
- FEIS 12 Hazardous Materials
- FEIS 13 Infrastructure
- FEIS 14 Solid Waste and Sanitation Services
- FEIS 15 Energy
- FEIS 16 Traffic and Parking
- FEIS 17 Transit and Pedestrians
- FEIS 18 Air Quality and Greenhouse Gas Emissions
- FEIS 19 Noise
- FEIS 20 Construction Impacts
- FEIS 21 Public Health
- FEIS 22 Mitigation
- FEIS 23 Unavoidable Adverse Impacts
- FEIS 24 Alternatives
- FEIS 25 Growth-Inducing Aspects of the Proposed Project
- FEIS 26 Irreversible and Irretrievable Commitment of Resources
- FEIS 27 Conceptual Analysis of the Proposed Zoning Text Amendments
- FEIS 28 Response to Comments on the Draft Scope of Work and DEIS
- FEIS Appendix A Zoning Text
- FEIS Appendix B Historic Resources
- FEIS Appendix C Transportation Technical Memos and Analyses
- FEIS Appendix D Infrastructure
- FEIS Appendix E Air Quality and Greenhouse Gas Emissions
- FEIS Appendix F Noise
- FEIS Appendix G Construction Noise
- FEIS Appendix H Written Comments on the DSOW
- FEIS Appendix I Written Comments on the DEIS
- FEIS Cover Page and Table of Contents
- FEIS Foreword
- FEIS Notice of Completion Jul 2, 2010
- Final Scope of Work Feb 5, 2010
- Lead Agency Letter Dec 19, 2008
- Notice of Scoping Meeting Dec 19, 2008
- Positive Declaration Dec 19, 2008
Hearings and presentations1 document
- Notice of Public Hearing May 3, 2010
Source: the NYC Department of City Planning's Zoning Application Portal, project P2010M0028, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.