REZONE THE EXISTING C1-4 OVERLAY IN AN R7-1 ZONE TO C8-3 TO*LEGALIZE AN EXISTING AUTOMOBILE REPAIR FACILITY (UG 16)

Outcome
Approved
Zoning map ULURP
C980391ZMX
Rezoned area
0.4 acres
Law firm
—

Timeline

6 months from filing to approval1 month to certification · 5 months of public review

Application and environmental review1 month

  1. Application filedFeb 9, 1998The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewJan 31, 1997 · through May 12, 1997An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMar 16, 1998 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardApr 30, 1998 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentMay 29, 1998 · FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingJun 3, 1998 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteJul 22, 1998 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilAug 27, 1998 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorSep 1, 1998 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedSep 1, 1998

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDefrin Realty CoPrivate applicant

Environmental review CEQR 97DCP036AX · zoning map amendment C980391ZMX.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1998X0223, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.