1601,1616,1623 8th Ave

CHANGE R-5 TO R-6, NEW 7-ST SR CITIZEN HSG - 200 RENTAL*DU'S(LOT 1)

Outcome
Approved
Zoning map ULURP
C780025ZMK
Rezoned area
—
Law firm
—

Timeline

5 months from filing to approval28 days to certification · 4 months of public review

Application and environmental review28 days

  1. Application filedJan 9, 1978The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewFeb 6, 1978The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review4 months

  1. Community boardMar 27, 1978 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingApr 26, 1978 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteMay 17, 1978 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedJun 9, 1978

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantProgress Of Peoples Dev CorpPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1978K0311, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.