A zoning map amendment from R4/C1-2 to R6A/C2-4 and a text amendment to map a Mandatory Inclusionary Housing Area (ZR Appendix F) to facilitate a new five-story building (approx. 129,000 square feet and 148 DUs) are being sought by private applicant Coyle Properties LLC, at 2134 Coyle Street, Community District 15, Brooklyn.

Outcome
Approved
Zoning map ULURP
C210239ZMK
Rezoned area
1.6 acres
Law firm
—

Timeline

1 year, 2 months from filing to approval8 months to certification · 6 months of public review

Application and environmental review8 months

  1. Application filedDec 31, 2020The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewMay 13, 2021 · through Jun 8, 2021An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewSep 7, 2021 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardOct 27, 2021 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentNov 25, 2021 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingDec 1, 2021 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteJan 5, 2022 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilFeb 17, 2022 · CC refers modification application back to CPCThe Council reviews rezonings and votes within 50 days.
  6. MayorMar 1, 2022 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedMar 18, 2022

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantCoyle Properties LLCPrivate applicant
Applicant's contactNeil WeisbardPrimary contact on the City's record
Environmental consultant—Named on the environmental assessment statement (21DCP123K_Certified_EAS_08272021.pdf, p. 2)

Environmental review CEQR 21DCP123K · zoning map amendment C210239ZMK.

City Documents

Application and notices25 documents
Environmental review3 documents
Approvals and reports1 document