410-478 W23rd St, & 9th Ave
84-078M: REZONING OF SOUTHSIDE OF WEST 23RD STREET FROM R8 TO R7-2
- Outcome
- Approved
- Zoning map ULURP
- I840711ZMM
- Rezoned area
- —
- Law firm
- —
Timeline
3 years, 7 months from filing to approval3 years, 7 months to certification · 0 days of public review
Application and environmental review3 years, 7 months
- Application filedMar 7, 1984The applicant files the land use application with the Department of City Planning.
- Environmental reviewMar 8, 1984 · through May 2, 1984An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewOct 19, 1987The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review0 days
- Community boardUp to 60 days for the community board's advisory recommendation.
- Borough presidentUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingThe Planning Commission's public hearing.
- City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedOct 19, 1987
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 84-078M · zoning map amendment I840711ZMM.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1984M0650, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.