Timeline

8 months from filing to approval2 months to certification · 6 months of public review

Application and environmental review2 months

  1. Application filedJan 6, 1983The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMar 14, 1983 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardMay 23, 1983 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJul 18, 1983 · Hearing ContinuedThe Planning Commission's public hearing.
  3. City Planning Commission voteJul 18, 1983 · Approval with ModificationThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedSep 15, 1983

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcp-BklynDepartment of City Planning

Source: the NYC Department of City Planning's Zoning Application Portal, project P1983K0451, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.