THE CONDO BOOK PROJECT

58th Bet 52nd Rd & 52nd Ave

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

CHANGE M3-1 TO M1-1 FOR DEPARTMENT OF SANITATION REPAIR SHOP

Outcome
Approved
Zoning map ULURP
C830495ZMQ
Rezoned area
3.7 acres
Law firm
—

Timeline

7 months from filing to approval2 months to certification · 5 months of public review

Application and environmental review2 months

  1. Application filedJan 7, 1983The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMar 7, 1983 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardMay 11, 1983 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJul 11, 1983 · Hearing ContinuedThe Planning Commission's public hearing.
  3. City Planning Commission voteJul 11, 1983 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedAug 18, 1983

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDsnyOther Public Agency

Source: the NYC Department of City Planning's Zoning Application Portal, project P1983Q0454, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.