606 West 57th Street (Tf Cornerstone)
This is a zoning map amendment from M1-5/M2-3 to C4-7 with nclusionary Housing to facilitate the development of a tower with approximately 1,000 residential units on the south side of West 57th Street between Eleventh Avenue and Twelfth Avenue.
- Outcome
- Approved
- Zoning map ULURP
- C130336ZMM
- Rezoned area
- 3.4 acres
- Law firm
- —
Timeline
1 year, 3 months from filing to approval5 months to certification · 10 months of public review
Application and environmental review5 months
- Application filedMay 21, 2013The applicant files the land use application with the Department of City Planning.
- Environmental reviewJan 29, 2013 · through Mar 14, 2014An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewOct 21, 2013 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review10 months
- Community boardDec 17, 2013 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
- Borough presidentDec 31, 2013 · Conditional FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingMar 17, 2014 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteMar 17, 2014 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilMay 19, 2014 · Adopted with ModificationsThe Council reviews rezonings and votes within 50 days.
- MayorMay 19, 2014 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedSep 4, 2014
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 13DCP080M · zoning map amendment C130336ZMM.
Condo Buildings Here
1 NYC condo building with an offering plan accepted after this rezoning took effect stand on its blocks or inside its area.
| Condominium | Accepted | Units | Where |
|---|---|---|---|
| 611 W 56th Street Condominium611 West 56th Street · Manhattan | 2019 | 80 | On the rezoned blocks |
City Documents
Environmental review68 documents
- DEIS 00 Executive Summary
- DEIS 01 Project Description
- DEIS 02 Land Use, Zoning, and Public Policy
- DEIS 03 Socioeconomic Conditions
- DEIS 04 Community Facilities
- DEIS 05 Open Space
- DEIS 06 Shadows
- DEIS 07 Historic and Cultural Resources
- DEIS 08 Urban Design and Visual Resources
- DEIS 09 Hazardous Materials
- DEIS 10 Water and Sewer Infrastructure
- DEIS 11 Transportation
- DEIS 12 Air Quality
- DEIS 13 Greenhouse Gas Emissions
- DEIS 14 Noise
- DEIS 15 Public Health
- DEIS 16 Neighborhood Character
- DEIS 17 Construction
- DEIS 18 Alternatives
- DEIS 19 Mitigation
- DEIS 20 Unavoidable Adverse Impacts
- DEIS 21 Growth-Inducing Aspects of the Proposed Actions
- DEIS 22 Irreversible and Irretrievable Commitments of Resources
- DEIS Appendix A Proposed Zoning Text Amendment
- DEIS Appendix B Agency Correspondence
- DEIS Cover Page and Table of Contents
- DEIS Notice Of Completion Oct 18, 2013
- Draft Scope Of Work Mar 21, 2013
- EAS Mar 21, 2013
- FEIS 00 Executive Summary
- FEIS 01 Project Description
- FEIS 02 Land Use, Zoning and Public Policy
- FEIS 03 Socioeconomic Conditions
- FEIS 04 Community Facilities
- FEIS 05 Open Space
- FEIS 06 Shadows
- FEIS 07 Historic and Cultural Resources
- FEIS 08 Urban Design and Visual Resources
- FEIS 09 Hazardous Materials
- FEIS 10 Water and Sewer Infrastructure
- FEIS 11 Transportation
- FEIS 12 Air Quality
- FEIS 13 Greenhouse Gas Emissions
- FEIS 14 Noise
- FEIS 15 Public Health
- FEIS 16 Neighborhood Character
- FEIS 17 Construction
- FEIS 18 Alternatives
- FEIS 19 Mitigation
- FEIS 20 Unavoidable Adverse Impacts
- FEIS 21 Growth-Inducing Aspects of the Proposed Actions
- FEIS 22 Irreversible and Irretrievable Commitments of Resources
- FEIS 23 Response to Comments
- FEIS Appendix A Proposed Zoning Text Amendment
- FEIS Appendix B Agency Correspondence
- FEIS Appendix C Development Site 2 Residential Mixed-Use Development Illustrative Diagrams
- FEIS Appendix D Waterfront Revitalization Program Consistency Assessment Form
- FEIS Appendix E Comments on the DEIS
- FEIS Appendix F Development Site 2 Conceptual Analysis
- FEIS Cover Page and Table of Contents
- FEIS Foreword
- FEIS Notice Of Completion Mar 7, 2014
- Final Scope Of Work Oct 18, 2013
- Lead Agency Letter Mar 21, 2013
- Notice of Scoping Meeting Mar 25, 2013
- Positive Declaration Mar 21, 2013
- Tech Memo Mar 14, 2014
- Tech Memo May 1, 2014
Hearings and presentations1 document
- Notice of Public Hearing Jan 22, 2014
Source: the NYC Department of City Planning's Zoning Application Portal, project P2012M0635, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.