THE CONDO BOOK PROJECT
Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

08DCP067X: ZONING MAP AMENDMENT FROM C8-1 TO R6 TO R6/C2-4

Outcome
Approved
Zoning map ULURP
C090143ZMX
Rezoned area
1.2 acres
Law firm
—

Timeline

1 year, 8 months from filing to approval1 year, 2 months to certification · 6 months of public review

Application and environmental review1 year, 2 months

  1. Application filedOct 10, 2008The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewApr 29, 2008An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewJan 4, 2010 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardMar 3, 2010 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentApr 2, 2010 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingApr 28, 2010 · Hearing ClosedThe Planning Commission's public hearing.
  4. City CouncilJun 29, 2010 · AdoptedThe Council reviews rezonings and votes within 50 days.
  5. MayorJul 6, 2010 · No VetoThe mayor may veto within 5 days; the Council can override.
  6. ApprovedJul 6, 2010

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

Applicant625 Fordham LLCPrivate applicant

Environmental review CEQR 08DCP067X · zoning map amendment C090143ZMX.

Source: the NYC Department of City Planning's Zoning Application Portal, project P2009X0090, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.