875 3rd Ave E/S 3rd Ave Bet 52 & 53 Sts
CHANGE R8 & C6-6CR TO C6-6, TO PERMIT CONST OF 28-STY OFFICE*BLDG (POPS)
- Outcome
- Approved
- Zoning map ULURP
- C800753ZMM
- Rezoned area
- —
- Law firm
- —
Timeline
6 months from filing to approval1 month to certification · 4 months of public review
Application and environmental review1 month
- Application filedJul 30, 1980The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewSep 29, 1980 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardDec 8, 1980 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJan 26, 1981 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJan 26, 1981 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedFeb 26, 1981
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantKenvic AssocPrivate applicant
Source: the NYC Department of City Planning's Zoning Application Portal, project P1981M0111, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.