Timeline
1 year, 3 months from filing to approval10 months to certification · 4 months of public review
Application and environmental review10 months
- Application filedMay 16, 1990The applicant files the land use application with the Department of City Planning.
- Environmental reviewMar 21, 1990An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewApr 1, 1991 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardApr 29, 1991 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentMay 8, 1991 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJul 8, 1991 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJul 8, 1991 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilAug 15, 1991 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorAug 20, 1991 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedAug 20, 1991
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 90-175R · zoning map amendment C900831ZMR.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1990R0653, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.