REZONE M1-5 TO C6-4, C6-2 TO FACILITATE THE DEV OF MULTI-USE*BLDGS TO BE IN HARMONY WITH JAVITS CONVENTION CENTER

Outcome
Approved
Zoning map ULURP
C891068ZMM
Rezoned area
11.5 acres
Law firm
—

Timeline

8 months from filing to approval2 months to certification · 5 months of public review

Application and environmental review2 months

  1. Application filedJun 22, 1989The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewSep 11, 1989 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardNov 20, 1989 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingNov 29, 1989 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteDec 27, 1989 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedFeb 22, 1990

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantMid-Town Devlpmnt Limited PartnershipPrivate applicant

Environmental review CEQR 86-249M · zoning map amendment C891068ZMM.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1989M0897, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.