86-121M: 310,000 SQ. FT. MIXED USE BUILDING; 310 DWELLING, 37 STORIES

Outcome
Approved
Zoning map ULURP
C861180ZMM
Rezoned area
1.4 acres
Law firm
—

Timeline

1 year, 8 months from filing to approval1 year, 2 months to certification · 5 months of public review

Application and environmental review1 year, 2 months

  1. Application filedJun 9, 1986The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewAug 17, 1987The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardOct 20, 1987 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingDec 21, 1987 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteDec 21, 1987 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedFeb 11, 1988

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantGlenwood Management Corp Et AlPrivate applicant

Environmental review CEQR 86-121M · zoning map amendment C861180ZMM.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1986M0985, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.