Bay St Landing

3RD MOD OF THE RESTR DECL & AND MOD OF THE ALTERNATE DEV*DECL IN ORDER TO REDUCE UNITS PLANNED FOR BLDGS FRM 428 TO

Outcome
Approved
Zoning map ULURP
M820697AZMR
Rezoned area
—
Law firm
—

Timeline

7 months from filing to approval5 months to certification · 2 months of public review

Application and environmental review5 months

  1. Application filedAug 6, 1984The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewFeb 5, 1982 · through Sep 20, 1982An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewJan 7, 1985The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review2 months

  1. City Planning Commission voteApr 3, 1985 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  2. City CouncilThe Council reviews rezonings and votes within 50 days.
  3. MayorThe mayor may veto within 5 days; the Council can override.
  4. ApprovedApr 3, 1985

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantKey Interntl Mfg IncPrivate applicant

Environmental review CEQR 82-076R · zoning map amendment M820697AZMR.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1985R0152, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.