Baybridge Shopping Center
REZONE FROM R5 TO C1-2 TO INCREASE SHOPPING CENTER
- Outcome
- Approved
- Zoning map ULURP
- C831771ZMQ
- Rezoned area
- 4 acres
- Law firm
- —
Timeline
1 year, 6 months from filing to approval1 year to certification · 5 months of public review
Application and environmental review1 year
- Application filedJun 30, 1983The applicant files the land use application with the Department of City Planning.
- Environmental reviewJul 26, 1983 · through Mar 21, 1984An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJul 23, 1984 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review5 months
- Community boardSep 24, 1984 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingNov 19, 1984 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteNov 19, 1984 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJan 10, 1985
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantMcgee & MorsalinoPrivate applicant
Environmental review CEQR 83-199Q · zoning map amendment C831771ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1983Q1691, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.