Bayside Rezoning
REZONE R4 TO R2, R3-1, R3-2 & R5B TO REFLECT MIX OF BLDG*TYPES & DENSITIES & CHANNEL HIGHER-DENSITY DEVELOPMENT
- Outcome
- Approved
- Zoning map ULURP
- C890609ZMQ
- Rezoned area
- 146.7 acres
- Law firm
- —
Timeline
6 months from filing to approval3 months to certification · 3 months of public review
Application and environmental review3 months
- Application filedFeb 22, 1989The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJun 5, 1989 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review3 months
- Community boardJul 24, 1989 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJul 26, 1989 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteAug 9, 1989 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedSep 14, 1989
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 89-271Q · zoning map amendment C890609ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1989Q0549, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.