THE CONDO BOOK PROJECT
Rezoned areaCondo buildingsBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

REZONING

Outcome
Approved
Zoning map ULURP
C850811ZMK
Rezoned area
7.1 acres
Law firm
—

Timeline

1 year, 2 months from filing to approval9 months to certification · 4 months of public review

Application and environmental review9 months

  1. Application filedApr 16, 1985The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewApr 18, 1985An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewJan 27, 1986 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review4 months

  1. Community boardMar 17, 1986 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingApr 9, 1986 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteApr 30, 1986 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedJun 17, 1986

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Environmental review CEQR 85-271K · zoning map amendment C850811ZMK.

Condo Buildings Here

2 NYC condo buildings with an offering plan accepted after this rezoning took effect stand inside its area.

CondominiumAcceptedUnitsWhere
142 North First Street Condominium142 North First Street · Brooklyn20128In the rezoned area
160-164 Grand Street Condominium160-164 Grand Street · Brooklyn200515In the rezoned area

City Documents

Environmental review1 document

Source: the NYC Department of City Planning's Zoning Application Portal, project P1985K0766, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.