THE CONDO BOOK PROJECT
Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

This is an application by the NYC Economic Development Corporation and DCAS, for a disposition, zoning text amendment (Appendix F - MIH), zoning map amendment (R6 to R7-2 and R7-2/C2-4 districts), a special permit (ZR Section 74-74 large scale general development) to facilitate the adaptive reuse and redevelopment of the Bedford Union Armory including 108,000 sf community facility use, 25,000 sf commercial use, and 362,000 sf of residential use (415 DU’s).

Outcome
Approved
Zoning map ULURP
C170416ZMK
Rezoned area
3.8 acres
Law firm
—

Timeline

6 months from filing to approval6 days to certification · 6 months of public review

Application and environmental review6 days

  1. Application filedMay 16, 2017The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 22, 2017 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardAug 11, 2017 · DisapprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentSep 1, 2017 · Conditional UnfavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingSep 19, 2017 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteOct 30, 2017 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilNov 30, 2017 · Adopted with ModificationsThe Council reviews rezonings and votes within 50 days.
  6. MayorDec 5, 2017 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedDec 5, 2017

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantNYC EdcOther Public Agency

Environmental review CEQR 16DME005K · zoning map amendment C170416ZMK.

Source: the NYC Department of City Planning's Zoning Application Portal, project P2016K0272, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.