Brighton-By-The-Sea
ACTIONS TO FACILITATE THE CONSTRUCTION OF 1,730 DWELLING UNITS IN 5 TOWERS & 2*BLDGS WITH ATTACHED TOWNHOUSES
- Outcome
- Approved
- Zoning map ULURP
- C900023ZMK
- Rezoned area
- —
- Law firm
- —
Timeline
6 months from filing to approval3 months to certification · 2 months of public review
Application and environmental review3 months
- Application filedJul 7, 1989The applicant files the land use application with the Department of City Planning.
- Environmental reviewJun 7, 1989 · through Aug 30, 1991An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewOct 30, 1989 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review2 months
- Community boardNov 27, 1989 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJan 22, 1990 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJan 22, 1990 · Fail to AdoptThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJan 22, 1990
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 89-299K · zoning map amendment C900023ZMK.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1990K0009, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.