Brownsville II Urp
CONSTRUCT 350 ROW HOUSES,MODERATE INCOME SINGLE FAMILY*DEVELOPMENT. PHASE 11 OF THE NEHEMIA PLAN
- Outcome
- Approved
- Zoning map ULURP
- C841021ZMK
- Rezoned area
- 8 acres
- Law firm
- —
Timeline
6 months from filing to approval1 month to certification · 4 months of public review
Application and environmental review1 month
- Application filedJun 1, 1984The applicant files the land use application with the Department of City Planning.
- Environmental reviewJan 25, 1983An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJul 23, 1984 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardOct 1, 1984 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingOct 17, 1984 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteOct 31, 1984 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedDec 6, 1984
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 83-010K · zoning map amendment C841021ZMK.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1984K0915, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.