C-O-P/Am & G Waterproofing
UNRESTRICTED DISPO OF 5 CITY-OWNED LOTS TO EDC
- Outcome
- Approved
- Zoning map ULURP
- C040124ZMK
- Rezoned area
- 3.5 acres
- Law firm
- Wachtel & Masyr
Timeline
9 months from filing to approval4 months to certification · 5 months of public review
Application and environmental review4 months
- Application filedSep 22, 2003The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 26, 2004 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review5 months
- Community boardMar 2, 2004 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentMar 30, 2004 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingApr 14, 2004 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteMay 12, 2004 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilJun 21, 2004 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorJun 28, 2004 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 28, 2004
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantErma RealtyOther Public Agency
Environmental review CEQR 03DME017K · zoning map amendment C040124ZMK.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2004K0088, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.