C-O-P/East Harlem Parking Lot
90-116M: TO DEVELOP AN OFF-STREET PARKING FACILITY TO PROVIDE SAFE AN D SECURE PARKING FOR AREA SHOPPERS
- Outcome
- Approved
- Zoning map ULURP
- I900496ZMM
- Rezoned area
- —
- Law firm
- —
Timeline
5 years, 11 months from filing to approval5 years, 11 months to certification · 0 days of public review
Application and environmental review5 years, 11 months
- Application filedJan 10, 1990The applicant files the land use application with the Department of City Planning.
- Environmental reviewJan 9, 1990An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 3, 1996The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review0 days
- Community boardUp to 60 days for the community board's advisory recommendation.
- Borough presidentUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingThe Planning Commission's public hearing.
- City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJan 3, 1996
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 90-116M · zoning map amendment I900496ZMM.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1990M0408, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.