THE CONDO BOOK PROJECT

Calvary Baptist Church Houses

1ST MODIFICATION SO THAT BLDG & SITE PLAN MAY CONFORM TO R-5*ZONING UNDER SECTION 202/8

Outcome
Approved
Zoning map ULURP
M820224AZMQ
Rezoned area
—
Law firm
—

Timeline

2 years, 3 months from filing to approval4 months to certification · 1 year, 11 months of public review

Application and environmental review4 months

  1. Application filedDec 11, 1987The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewFeb 23, 1982An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewApr 18, 1988The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review1 year, 11 months

  1. City Planning Commission voteApr 3, 1989 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  2. City CouncilThe Council reviews rezonings and votes within 50 days.
  3. MayorThe mayor may veto within 5 days; the Council can override.
  4. ApprovedMar 29, 1990

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantCalvary Baptist ChurchPrivate applicant

Environmental review CEQR 82-047Q · zoning map amendment M820224AZMQ.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1988Q0398, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.