CHANGE M1-1 & R3-2 TO C3 FOR PROPOSED LARGE-SCALE*DEVELOPMENT

Outcome
Approved
Zoning map ULURP
C800103ZMX
Rezoned area
5.9 acres
Law firm
—

Timeline

1 year, 1 month from filing to approval3 months to certification · 9 months of public review

Application and environmental review3 months

  1. Application filedFeb 7, 1980The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 27, 1980 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review9 months

  1. Community boardJul 9, 1980 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingAug 18, 1980 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteAug 18, 1980 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedMar 17, 1981

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantThe Boatyard AssociatesPrivate applicant

Condo Buildings Here

1 NYC condo building with an offering plan accepted after this rezoning took effect stand inside its area.

CondominiumAcceptedUnitsWhere
Boatyard Condo210 Carroll St. · Bronx19820In the rezoned area

Source: the NYC Department of City Planning's Zoning Application Portal, project P1980X0709, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.