06DCP002K: TO REZONE FROM M1-1 TO R6 TO FACILITATE THE CONSTRUCTION OF TWO MULTI-FAMILY RESIDENTIAL BUILDINGS CONTAINING EIGHT DWEL LING UNITS ON THE SITE

Outcome
Approved
Zoning map ULURP
C060018ZMK
Rezoned area
0.3 acres
Law firm
—

Timeline

1 year, 8 months from filing to approval1 year, 2 months to certification · 5 months of public review

Application and environmental review1 year, 2 months

  1. Application filedJul 12, 2005The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewJul 18, 2005An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewOct 10, 2006 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardDec 18, 2006 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentDec 27, 2006 · FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingJan 24, 2007 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteFeb 28, 2007 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilMar 28, 2007 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorApr 3, 2007 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedApr 3, 2007

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

Applicant37 Carroll St LLC, 39 Carroll St, LLCPrivate applicant

Environmental review CEQR 06DCP002K · zoning map amendment C060018ZMK.

Condo Buildings Here

1 NYC condo building with an offering plan accepted after this rezoning took effect stand on its blocks or inside its area.

CondominiumAcceptedUnitsWhere
37 Carroll Street Condominium37 Carroll Street · Brooklyn20194On the rezoned blocks

Source: the NYC Department of City Planning's Zoning Application Portal, project P2006K0015, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.