THE CONDO BOOK PROJECT

City Island Ave Bet Beach & Bowne Sts

CHANGE M1 TO C2*(LOT 13)

Outcome
Approved
Zoning map ULURP
A760041ZMX
Rezoned area
—
Law firm
—

Timeline

1 year, 4 months from filing to approval1 year, 4 months to certification · 0 days of public review

Application and environmental review1 year, 4 months

  1. Application filedAug 2, 1976The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewDec 6, 1977The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review0 days

  1. Community boardUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingThe Planning Commission's public hearing.
  4. City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilThe Council reviews rezonings and votes within 50 days.
  6. MayorThe mayor may veto within 5 days; the Council can override.
  7. ApprovedDec 6, 1977

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantKretzer Boat Works, IncPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1977X0036, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.