College Point Rezoning
87-047Q: REZONE R4 IN ORDER TO BUILD 5 3-STORY MULTIPLE DWELLINGS TB4060. TL1-34.
- Outcome
- Approved
- Zoning map ULURP
- C870163ZMQ
- Rezoned area
- 4.6 acres
- Law firm
- —
Timeline
1 year, 9 months from filing to approval1 year, 5 months to certification · 4 months of public review
Application and environmental review1 year, 5 months
- Application filedAug 19, 1986The applicant files the land use application with the Department of City Planning.
- Environmental reviewAug 28, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 25, 1988 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardMar 24, 1988 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingApr 20, 1988 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteMay 18, 1988 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 9, 1988
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 87-047Q · zoning map amendment C870163ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1987Q0144, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.