Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

This is a private application by the Upper Manhattan Development Corporation requesting a zoning map amendment from C8-3 to R7D and R7D/C1-4 to facilitate the construction of a mixed-use development with 265 dwelling units and convenience retail stores. The project also maps Mandatory Inclusionary Housing, which requires a zoning text amendment of Appendix F of the Zoning Resolution. The project is located in the Concourse Village neighborhood within Community District 4 of the Bronx.

Outcome
Approved
Zoning map ULURP
C150312ZMX
Rezoned area
7.6 acres
Law firm
—

Timeline

1 year, 7 months from filing to approval1 year, 1 month to certification · 5 months of public review

Application and environmental review1 year, 1 month

  1. Application filedMar 26, 2015The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewApr 7, 2016 · through Apr 29, 2016An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMay 23, 2016 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardJul 18, 2016 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentAug 19, 2016 · FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingSep 7, 2016 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteOct 5, 2016 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilNov 21, 2016 · Adopted with ModificationsThe Council reviews rezonings and votes within 50 days.
  6. MayorNov 21, 2016 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedNov 21, 2016

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantUpper Manhattan Development Corp.Private applicant

Environmental review CEQR 16DCP146X · zoning map amendment C150312ZMX.

City Documents

Environmental review5 documents

Source: the NYC Department of City Planning's Zoning Application Portal, project P2013X0135, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.