Coney Island Commons
09HPD021K: ZONING MAP AMENDMENT TO CHAGNE AN EXISTING R6/C1-2 TO R7-2/C 1-2
- Outcome
- Approved
- Zoning map ULURP
- C090250ZMK
- Rezoned area
- 3 acres
- Law firm
- —
Timeline
5 months from filing to approval18 days to certification · 4 months of public review
Application and environmental review18 days
- Application filedDec 18, 2008The applicant files the land use application with the Department of City Planning.
- Environmental reviewOct 24, 2008An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 5, 2009 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardJan 29, 2009 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentMar 2, 2009 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingMar 4, 2009 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteApr 1, 2009 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilMay 20, 2009 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorMay 26, 2009 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedMay 26, 2009
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 09HPD021K · zoning map amendment C090250ZMK.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2009K0165, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.