Coney Island Ura
RESTRICTED DISPO OF 13 SITES FOR RESIDENTIAL/COMMERCIAL*USES INCLUDING SITE 29
- Outcome
- Approved
- Zoning map ULURP
- C870923ZMK
- Rezoned area
- 1.5 acres
- Law firm
- —
Timeline
1 year from filing to approval6 months to certification · 6 months of public review
Application and environmental review6 months
- Application filedJun 1, 1987The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewDec 7, 1987 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardFeb 15, 1988 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingApr 11, 1988 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteApr 11, 1988 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 9, 1988
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantHpdOther Public Agency
Source: the NYC Department of City Planning's Zoning Application Portal, project P1987K0793, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.