THE CONDO BOOK PROJECT

Convention Center Spec Dist

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

REZONE M1-5 TO M1-5 WITH SPECIAL PURPOSE DISTRICT CC OVERLAY*TO EASE THE MOVEMENT OF PEDESTRIANS & IMPROVE PEDESTRIAN*ACCESS TO THE CONVENTION CENTER

Outcome
Approved
Zoning map ULURP
C900052ZMM
Rezoned area
61.2 acres
Law firm
—

Timeline

7 months from filing to approval2 months to certification · 5 months of public review

Application and environmental review2 months

  1. Application filedJul 14, 1989The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewSep 22, 1989The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardNov 20, 1989 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingNov 29, 1989 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteDec 27, 1989 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedFeb 22, 1990

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Environmental review CEQR 86-249M · zoning map amendment C900052ZMM.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1990M0027, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.