Costco Enlargement
07DCP067R: CONSTRUCTION OF A NEW BUILDING ADDITION OF 21,866 GSF TO THE EXISTING 121,216 GSF BUILDING; Additional Other #(s): 060374B
- Outcome
- Approved
- Zoning map ULURP
- M860374DZMR
- Rezoned area
- —
- Law firm
- —
Timeline
3 years, 1 month from filing to approval2 years, 9 months to certification · 4 months of public review
Application and environmental review2 years, 9 months
- Application filedApr 20, 2007The applicant files the land use application with the Department of City Planning.
- Environmental reviewApr 19, 2007An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 25, 2010The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardNo date on recordUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingApr 14, 2010 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteMay 12, 2010 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 3, 2010
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 07DCP067R · zoning map amendment M860374DZMR.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2007R0308, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.