CHANGE R4 TO R1-2, IN THE NA-2 DISTRICT OF RIVERDALE

Outcome
Approved
Zoning map ULURP
C780085ZMX
Rezoned area
5.3 acres
Law firm
—

Timeline

2 years, 5 months from filing to approval2 years, 2 months to certification · 3 months of public review

Application and environmental review2 years, 2 months

  1. Application filedFeb 23, 1978The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 12, 1980 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardJun 6, 1980 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJul 9, 1980 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteJul 9, 1980 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedAug 21, 1980

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantFriends Of The Green BeltPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1978X0395, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.