1ST MOD TO A ZO AMENDMNT TO REDESIGN BLDG ON FRESH POND RD,*CHANGE LANDSCAPE PLAN & SHIFT PKING SPACES TO ALLOW BETTER*TRAFFIC FLOW & DEMOLISH COAL STORAGE SILOS. BL3637 LOT1,2

Outcome
Approved
Zoning map ULURP
M830193AZMQ
Rezoned area
—
Law firm
—

Timeline

11 months from filing to approval4 months to certification · 6 months of public review

Application and environmental review4 months

  1. Application filedNov 3, 1986The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewSep 13, 1982An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMar 16, 1987The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. City Planning Commission voteOct 7, 1987 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  2. City CouncilThe Council reviews rezonings and votes within 50 days.
  3. MayorThe mayor may veto within 5 days; the Council can override.
  4. ApprovedOct 7, 1987

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantRose-Polly Prop, IncPrivate applicant

Environmental review CEQR 82-270Q · zoning map amendment M830193AZMQ.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1987Q0329, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.