Dntr Tire, Inc
PROPOSED AUTO SERVICE ESTABLISHMENT CHANGE R3-2 TO C8
- Outcome
- Approved
- Zoning map ULURP
- C841073ZMQ
- Rezoned area
- 2.5 acres
- Law firm
- —
Timeline
9 months from filing to approval5 months to certification · 4 months of public review
Application and environmental review5 months
- Application filedJun 18, 1984The applicant files the land use application with the Department of City Planning.
- Environmental reviewJun 20, 1984An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewNov 26, 1984 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardDec 28, 1984 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingFeb 26, 1985 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteFeb 26, 1985 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedMar 28, 1985
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantAdams, GeorgeDepartment of City Planning
Environmental review CEQR 84-196Q · zoning map amendment C841073ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1984Q0959, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.