Durst W57
This is a zoning map amendment to rezone a M1-5 district to C4-7 and a modification to a previously-approved Large-Scale General Development to facilitate the redevelopment of a new residential building (Via 57) with some office and retail uses.
- Outcome
- Approved
- Zoning map ULURP
- M010148AZMM
- Rezoned area
- 1.7 acres
- Law firm
- —
Timeline
1 year from filing to approval1 month to certification · 10 months of public review
Application and environmental review1 month
- Application filedJun 6, 2012The applicant files the land use application with the Department of City Planning.
- Environmental reviewAug 8, 2011 · through Jul 11, 2012An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJul 11, 2012The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review10 months
- Community boardSep 19, 2012 · DisapprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentOct 19, 2012 · Conditional FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingOct 17, 2012 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteDec 19, 2012 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilFeb 6, 2013 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorFeb 12, 2013 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 7, 2013
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 12DCP020M · zoning map amendment M010148AZMM.
City Documents
Environmental review61 documents
- Draft Scope of Work Sep 1, 2011
- DSEIS 00 Executive Summary
- DSEIS 01 Project Description
- DSEIS 02 Land Use, Zoning, and Public Policy
- DSEIS 03 Socioeconomic Conditions
- DSEIS 04 Community Facilities and Services
- DSEIS 05 Open Space
- DSEIS 06 Shadows
- DSEIS 07 Historic and Cultural Resources
- DSEIS 08 Urban Design and Visual Resources
- DSEIS 09 Hazardous Materials
- DSEIS 10 Transportation
- DSEIS 11 Air Quality
- DSEIS 12 Greenhouse Gas Emissions and Climate Change
- DSEIS 13 Noise
- DSEIS 14 Public Health
- DSEIS 15 Neighborhood Character
- DSEIS 16 Construction
- DSEIS 17 Alternatives
- DSEIS 18 Growth-Inducing Aspects of the Proposed Actions
- DSEIS 19 Irreversible and Irretrievable Commitment of Resources
- DSEIS 20 Mitigation Measures
- DSEIS Appendix A Agency Correspondence
- DSEIS Appendix B Noise
- DSEIS Cover Page and Table of Contents
- DSEIS Notice of Completion Jul 11, 2012
- EAS Sep 1, 2011
- Final Scope of Work Jul 11, 2012
- FSEIS 00 Executive Summary
- FSEIS 01 Project Description
- FSEIS 02 Land Use, Zoning, and Public Policy
- FSEIS 03 Socioeconomic Conditions
- FSEIS 04 Community Facilities and Services
- FSEIS 05 Open Space
- FSEIS 06 Shadows
- FSEIS 07 Historic and Cultural Resources
- FSEIS 08 Urban Design and Visual Resources
- FSEIS 09 Hazardous Materials
- FSEIS 10 Transportation
- FSEIS 11 Air Quality
- FSEIS 12 Greenhouse Gas Emissions and Climate Change
- FSEIS 13 Noise
- FSEIS 14 Public Health
- FSEIS 15 Neighborhood Character
- FSEIS 16 Construction
- FSEIS 17 Alternatives
- FSEIS 18 Growth-Inducing Aspects of the Proposed Actions
- FSEIS 19 Irreversible and Irretrievable Commitment of Resources
- FSEIS 20 Mitigation Measures
- FSEIS 21 Modifications to the Proposed Project
- FSEIS 22 Response to Comments on the DSEIS and Draft Scope of Work
- FSEIS Appendix A Agency Correspondence
- FSEIS Appendix B Air Quality and Noise
- FSEIS Appendix C Written Comments on the DSEIS and Draft Scope of Work
- FSEIS Cover Page and Table of Contents
- FSEIS Foreword
- FSEIS Notice of Completion Dec 7, 2012
- Lead Agency Letter Sep 1, 2011
- Positive Declaration Sep 1, 2011
- Revised Tech Memo Aug 3, 2016
- Tech Memo Apr 21, 2016
Hearings and presentations1 document
- Notice of Public Hearing Oct 15, 2012
Source: the NYC Department of City Planning's Zoning Application Portal, project P2012M0258, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.