E179th St, Monterey Ave, E178th St, 3rd Ave

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

CHANGE C8-5 TO R7-1,ESTABLISHING WITHIN PROPOSED R7-1 A*C2-3 DIST

Outcome
Approved
Zoning map ULURP
C800337ZMX
Rezoned area
1.1 acres
Law firm
—

Timeline

3 months from filing to approval3 days to certification · 3 months of public review

Application and environmental review3 days

  1. Application filedApr 4, 1980The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewApr 7, 1980 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardJun 16, 1980 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJun 18, 1980 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteJun 18, 1980 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedJul 17, 1980

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Source: the NYC Department of City Planning's Zoning Application Portal, project P1980X0878, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.