95DCP053M: PROPOSE TO REZONE THE EAST 14TH STREET CORRIDOR BETWEEN UNIV ERSITY PLACE AND AVENUE C FROM C6-1 TO C1-9A, C6-3X, AND C6- 2A; AND FROM R7-2 TO C1-6A, AND C1-7A

Outcome
Approved
Zoning map ULURP
C950443ZMM
Rezoned area
50.6 acres
Law firm
—

Timeline

7 months from filing to approval27 days to certification · 6 months of public review

Application and environmental review27 days

  1. Application filedApr 25, 1995The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewApr 28, 1995An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMay 22, 1995 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardJul 31, 1995 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentAug 30, 1995 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingOct 30, 1995 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteOct 30, 1995 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilDec 7, 1995 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorDec 12, 1995 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedDec 12, 1995

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Environmental review CEQR 95DCP053M · zoning map amendment C950443ZMM.

Condo Buildings Here

8 NYC condo buildings with an offering plan accepted after this rezoning took effect stand inside its area.

CondominiumAcceptedUnitsWhere
Copper Building Condominium215-217 Avenue B · Manhattan200917In the rezoned area
Union Square Flats Condo/123 Third Condo123 Third Avenue · Manhattan200847In the rezoned area
137 East 13 Street Condominium137 East 13th Street · Manhattan20069In the rezoned area
One Ten Third Condominium108-112 Third Avenue · Manhattan200676In the rezoned area
Building Condominium (A)425 East 13th Street · Manhattan200684In the rezoned area
Brownstone , East Village Condominium224 East 14th Street · Manhattan20064In the rezoned area
Stuyvesant Park Condominium240-242 East 15th Street · Manhattan200616In the rezoned area
Astor House Condo217 Second Avenue · Manhattan19990In the rezoned area

Source: the NYC Department of City Planning's Zoning Application Portal, project P1995M0298, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.