REZO FROM C-3 TO C8-1 FOR RETAIL STORE,245 PKING SPACES,*PROMENADE & UPGRADE EXIST MARINA

Outcome
Approved
Zoning map ULURP
C840631ZMK
Rezoned area
6.4 acres
Law firm
—

Timeline

9 months from filing to approval7 months to certification · 2 months of public review

Application and environmental review7 months

  1. Application filedFeb 15, 1984The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewDec 13, 1983An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewSep 17, 1984 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review2 months

  1. Community boardOct 9, 1984 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingNov 5, 1984 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteNov 5, 1984 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedDec 6, 1984

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantMjm DistributorsPrivate applicant

Environmental review CEQR 83-342K · zoning map amendment C840631ZMK.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1984K0581, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.