Foodways

URP TO REFLECT ELIMINATION OF SITE 8A & ITS INCORP INTO 9A &*SUBDIV OF 9 INTO 9A (RESDL) & 9B (RESDL/COMMRL)

Outcome
Approved
Zoning map ULURP
I860132ZMM
Rezoned area
—
Law firm
—

Timeline

3 years from filing to approval3 years to certification · 0 days of public review

Application and environmental review3 years

  1. Application filedAug 1, 1985The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewJan 18, 1984An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewAug 10, 1988The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review0 days

  1. Community boardUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingThe Planning Commission's public hearing.
  4. City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilThe Council reviews rezonings and votes within 50 days.
  6. MayorThe mayor may veto within 5 days; the Council can override.
  7. ApprovedAug 10, 1988

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantHpdOther Public Agency

Environmental review CEQR 84-014M · zoning map amendment I860132ZMM.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1986M0112, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.