THE CONDO BOOK PROJECT

Forest Hills/Rego Park Rezoning

Rezoned areaCondo buildingsBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

91-123Q: ULURO RELATED TO REZONE PORTIONS OF FOREST HILLS AND REGO PARK TO PROTECT SOUND ROWHOUSES FROM DEMOLITION AND REPLACEMENT AT GREATER BULKS AND DENSITY

Outcome
Approved
Zoning map ULURP
C910483ZMQ
Rezoned area
71.4 acres
Law firm
—

Timeline

1 year, 5 months from filing to approval11 months to certification · 6 months of public review

Application and environmental review11 months

  1. Application filedMay 2, 1991The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewFeb 28, 1991An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewApr 6, 1992 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardJun 2, 1992 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentJun 30, 1992 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingAug 24, 1992 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteAug 24, 1992 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilOct 8, 1992 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorOct 13, 1992 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedOct 13, 1992

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Environmental review CEQR 91-123Q · zoning map amendment C910483ZMQ.

Condo Buildings Here

1 NYC condo building with an offering plan accepted after this rezoning took effect stand inside its area.

CondominiumAcceptedUnitsWhere
Novo 64 Condominium64-05 Yellowstone Boulevard · Queens200793In the rezoned area

Source: the NYC Department of City Planning's Zoning Application Portal, project P1991Q0389, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.