THE CONDO BOOK PROJECT

Forster Ave & E. 89th St

CHANGE C8-1 TO R-4 TO PUT VACANT_LAND IN R-4 ZONE PROTECTING*NEW HOMES ADJ TO THE LOT & ENCOURAGE CONST OF NEW HOMES

Outcome
Approved
Zoning map ULURP
I780132ZMK
Rezoned area
—
Law firm
—

Timeline

6 years, 7 months from filing to approval7 months to certification · 6 years of public review

Application and environmental review7 months

  1. Application filedMar 29, 1978The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewNov 27, 1978The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 years

  1. Community boardUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingThe Planning Commission's public hearing.
  4. City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilThe Council reviews rezonings and votes within 50 days.
  6. MayorThe mayor may veto within 5 days; the Council can override.
  7. ApprovedNov 27, 1984

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantCbk18Other Public Agency

Source: the NYC Department of City Planning's Zoning Application Portal, project P1978K0441, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.