THE CONDO BOOK PROJECT

Hoe Ave Bet E163 St & Aldus St

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

ZO MAP CHANGE FORM R7-1 TO C4-4 TO PERMIT CONST OF PREV*APPVD PKING LOT

Outcome
Approved
Zoning map ULURP
C801102ZMX
Rezoned area
1 acres
Law firm
—

Timeline

3 months from filing to approval0 days to certification · 3 months of public review

Application and environmental review0 days

  1. Application filedDec 22, 1980The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewDec 22, 1980 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardJan 26, 1981 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingMar 4, 1981 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteMar 4, 1981 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedMar 26, 1981

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantCbx02Other Public Agency

Source: the NYC Department of City Planning's Zoning Application Portal, project P1981X0444, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.