Horace Harding Expway Rezoning
05DCP045Q: ZONING MAP AMEMDMENT TO ADD A C2-2 OVERLAY TO AN EXISTING R3 -2 DISTRICT
- Outcome
- Approved
- Zoning map ULURP
- C050190ZMQ
- Rezoned area
- 3.1 acres
- Law firm
- Sheldon Lobel, P.C.
Timeline
11 months from filing to approval5 months to certification · 5 months of public review
Application and environmental review5 months
- Application filedNov 24, 2004The applicant files the land use application with the Department of City Planning.
- Environmental reviewDec 2, 2004An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMay 23, 2005 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review5 months
- Community boardJul 13, 2005 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentJul 26, 2005 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingAug 24, 2005 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteSep 28, 2005 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilOct 27, 2005 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorNov 1, 2005 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedNov 1, 2005
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 05DCP045Q · zoning map amendment C050190ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2005Q0146, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.