Hudson Eldert Affordable Hsg

MODIFICATION OF A RESTRICTIVE DEC WHICH CURRENTLY LIMITS DEVELOPMENT ON THE SITE TO HOSPITAL AND HOSPITAL-RELATED USES AND IMPOSES THE ACCESSORY PARKING REQUIREMENTS

Outcome
Approved
Zoning map ULURP
M090312ZMK
Rezoned area
—
Law firm
—

Timeline

3 months from filing to approval2 months to certification · 1 month of public review

Application and environmental review2 months

  1. Application filedFeb 6, 2009The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewApr 7, 2009An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewApr 20, 2009The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review1 month

  1. City Planning Commission hearingApr 22, 2009 · Hearing ClosedThe Planning Commission's public hearing.
  2. City Planning Commission voteApr 22, 2009 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  3. City CouncilMay 20, 2009 · AdoptedThe Council reviews rezonings and votes within 50 days.
  4. MayorMay 26, 2009 · No VetoThe mayor may veto within 5 days; the Council can override.
  5. ApprovedMay 26, 2009

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantThe Hudson Co IncPrivate applicant

Environmental review CEQR 09DCP072K · zoning map amendment M090312ZMK.

Source: the NYC Department of City Planning's Zoning Application Portal, project P2009K0205, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.