Hunters Pt Expansion
85-279Q: REZONING TO CONSTRUCT A 40 STY OFFICE BLDG; Additional Other #(s): 860682B
- Outcome
- Approved
- Zoning map ULURP
- C860682ZMQ
- Rezoned area
- —
- Law firm
- —
Timeline
4 months from filing to approval1 month to certification · 3 months of public review
Application and environmental review1 month
- Application filedFeb 13, 1986The applicant files the land use application with the Department of City Planning.
- Environmental reviewMay 7, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMar 24, 1986 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review3 months
- Community boardMay 16, 1986 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJun 4, 1986 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJul 9, 1986
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 85-279Q · zoning map amendment C860682ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1986Q0591, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.