Imperial Plaza

86-300Q: 17 STORY PLUS MECHANICAL PENTHOUSE COMMERCIAL AND COMMUNITY FACILITY

Outcome
Approved
Zoning map ULURP
M790440BZMQ
Rezoned area
—
Law firm
McGee & Morsellino

Timeline

1 year, 8 months from filing to approval9 months to certification · 11 months of public review

Application and environmental review9 months

  1. Application filedApr 15, 1986The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewMay 20, 1986 · through Sep 23, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewFeb 2, 1987The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review11 months

  1. City Planning Commission hearingJul 20, 1987 · Hearing ClosedThe Planning Commission's public hearing.
  2. City Planning Commission voteJul 20, 1987 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  3. City CouncilThe Council reviews rezonings and votes within 50 days.
  4. MayorThe mayor may veto within 5 days; the Council can override.
  5. ApprovedJan 14, 1988

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantKew Gardens CoPrivate applicant
Land-use attorneyMcGee & MorsellinoSee the firm's rezoningsNamed in the City's applicant record

Environmental review CEQR 86-300Q · zoning map amendment M790440BZMQ.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1986Q0795, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.