Imperial Plaza
86-300Q: 17 STORY PLUS MECHANICAL PENTHOUSE COMMERCIAL AND COMMUNITY FACILITY
- Outcome
- Approved
- Zoning map ULURP
- M790440DZMQ
- Rezoned area
- —
- Law firm
- Rosenman & Colin
Timeline
1 year, 4 months from filing to approval8 months to certification · 8 months of public review
Application and environmental review8 months
- Application filedJan 25, 1991The applicant files the land use application with the Department of City Planning.
- Environmental reviewMay 20, 1986 · through Sep 23, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewOct 2, 1991The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review8 months
- Community boardNo date on recordUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingNo date on recordThe Planning Commission's public hearing.
- City Planning Commission voteOct 2, 1991 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 15, 1992
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 86-300Q · zoning map amendment M790440DZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1991Q0239, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.