Imperial Plaza

86-300Q: 17 STORY PLUS MECHANICAL PENTHOUSE COMMERCIAL AND COMMUNITY FACILITY

Outcome
Approved
Zoning map ULURP
M790440DZMQ
Rezoned area
—
Law firm
Rosenman & Colin

Timeline

1 year, 4 months from filing to approval8 months to certification · 8 months of public review

Application and environmental review8 months

  1. Application filedJan 25, 1991The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewMay 20, 1986 · through Sep 23, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewOct 2, 1991The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review8 months

  1. City Planning Commission voteOct 2, 1991 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  2. City CouncilThe Council reviews rezonings and votes within 50 days.
  3. MayorThe mayor may veto within 5 days; the Council can override.
  4. ApprovedJun 15, 1992

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

Applicant80-02 Leasehold CoPrivate applicant
Land-use attorneyRosenman & ColinSee the firm's rezoningsNamed in the City's applicant record

Environmental review CEQR 86-300Q · zoning map amendment M790440DZMQ.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1991Q0239, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.